“Surya” ordered to shut down the Pink Line electric train. Open for service on December 25, just 23 stations: PPTVHD36

“Surya” ordered to close the Pink Line electric train service. Hurry up to investigate the reason why the distribution rail broke and fell on the road. Only 23 stations will open on December 25.

Mr. Transport Minister Suriya Zhuangrungkit today, 24 December 2023 after visiting the section of the MRT Pink Line project in the Tiwanan Road area, at Samaki Station (PK 04) area at 4:45 am today, revealed there. An incident where a power distribution rail (conductor rail) fell down and fell to the ground. Also, the power lines connected to the Irrigation Market opposite were damaged due to which the bus service was affected.

Test runs of all electric railway stations on the Pink Line were temporarily closed.

Pink Line MRT apologizes for “power supply rails” failure, temporarily closes 7 stations

This is based on discussions with the Department of Rail Transport (MRTA), the Mass Rapid Transit Authority of Thailand (MRTA) and the project concessionaire, Northern Bangkok Monorail Company Limited (NBM). For the safety of passengers and fellow citizens, he ordered the closure of the Pink Line electric train service from 12:00 noon today to investigate the cause in detail.

Till December 25, 2023, a total of 23 stations will be opened for service from Seng Watana Station (PK08) – Minburi Station (PK30), Nonthapuri Government Central Station (PK01) to Pak Kret Bypass Station (PK07). All those 7 stations should be examined. and an initial evaluation for 7 days, then checked to ensure safety before re-opening the service

In this regard, it was emphasized that in case of a repeat incident, the penalty will be imposed as per the agreement. The cause of this incident, with conditions for the continued operation of the vehicle, is from the initial report, which stated that a foreign object was found in the rail inspection vehicle, which may have been caused by a crane that went to clear the area. Then polish the side wheel area to restore the road surface. As a result, the entire power supply rail line was cut off. No injuries were reported in the incident. But 3 cars were damaged in the area and electric wires were cut.

However, henceforth, there will be a road inspection vehicle inspecting the driveway at 4:00am each day before it opens for service. This is done to ensure that the Pink Line MRT project is completely safe for service and travel.